Task #13
closed
- Due date set to 06/20/2011
- Due date changed from 06/20/2011 to 07/04/2011
- Assignee set to Pat Mächler
As discussed on board meeting of 21.06.2011 Pat will create a draft due to the next board meeting
- % Done changed from 0 to 10
- Estimated time set to 1.00 h
- Due date changed from 07/04/2011 to 09/27/2011
- Due date changed from 09/27/2011 to 11/08/2011
- Due date changed from 11/08/2011 to 11/22/2011
- Due date changed from 11/22/2011 to 12/06/2011
- Due date changed from 12/06/2011 to 02/03/2012
- Priority changed from Normal to Low
- Pat: Had no time to work on further. Just a question: Should anything concerning competences be included?
- Thomas: It should not be definitive on certain points, but more overall, how should we could communicate, what can or should be internal, etc. Those things should be regulated I believe.
- Subject changed from Define joint communication strategy to Define joint communication strategy // Press work strategy
- Assignee changed from Pat Mächler to Denis Simonet
- Priority changed from Low to High
- Due date changed from 02/03/2012 to 05/31/2012
- Due date changed from 05/31/2012 to 06/19/2012
- Status changed from New to In Progress
- % Done changed from 10 to 70
- Due date changed from 06/19/2012 to 07/17/2012
- Status changed from In Progress to Closed
First work is done, we need to run the team now and then do modifications. This doesn't need to be tracked with this ticket, we have an own tracker. I'm going to put it on the agenda if anything needs to be discussed by the board.
Also available in: Atom