Activity
From 08/02/2016 to 08/31/2016
08/30/2016
-
06:15 PM Task #348 (Closed): Plan board meetings until 31-12-2016
- *December 2016*
Monday, 26 December 2016 08:00 CET
Sunday, 11 December 2016 21:00 CET
*November 2016*
Monda...
08/28/2016
-
12:58 AM Task #350 (Closed): IT - Servers relocations and consolidation
- h2. Introduction
Following a service outtage, Thomas has been made aware that the contract of our current server h... -
12:53 AM Decision #349 (New): Minimum Budget contingency 2016
- h2. Introduction
Prepare and present a minimum budget contingency for 2016
h2. Motives
There are expenditure... -
12:48 AM Task #348 (Closed): Plan board meetings until 31-12-2016
- h2. Introduction
In order to enable everyone to have an equal opportunity to participate to the board meetings, th... -
12:41 AM Task #347 (Closed): Communication plan development update
- h2. Introduction
The following is an action plan proposition.
The challenges in terms of communication are thre...
08/27/2016
-
05:55 PM Task #346 (In Progress): Member and contact databases updates
- Work is ongoing to collect and update contacts.
The sources used for the job comprise:
* https://api.piratimes... -
05:49 PM Task #345 (Closed): Execution of domiciliation - FYI
- Meeting with Dimitri Tzortzis is set for 31.08.2016. Domiciliation contract will be presented then and executed on be...
08/12/2016
-
08:57 PM Task #340 (In Progress): Development of a communication plan
-
08:55 PM Task #341 (In Progress): Development of an action plan
08/05/2016
-
02:06 PM Task #343: Renew all SSL certificates
- Installed Letsencrypt on the lists.pp-international.net and have configured it for
https://lists.pp-international.ne...
Also available in: Atom